Delmarva Power has submitted to the Maryland Public Service Commission an application to adjust energy distribution rates and implement a multi-year plan. A public prehearing conference on this matter is hereby set for Wednesday, June 15, 2022, 10 minutes after the conclusion of the Maryland Public Service Commission’s Administrative Meeting, which begins at 10:00 a.m., in the Frank O. Heintz Hearing Room, on the 16th Floor of the William Donald Schaefer Tower, 6 St. Paul Street, Baltimore, Maryland. Any petition to intervene must be filed with Andrew S. Johnston, Executive Secretary, Maryland Public Service Commission at the aforementioned address, by June 13.
Submitted application is reviewed for completeness.
Technical screening is performed, followed by site visits and approval to install your facilities.
Delmarva Power conducts design engineering and construction activities for the interconnection of your facility.
System installed by Developers. System should not be installed prior to receiving Approval to Install letter.
System is inspected by customer and DPL.
Subscriber is issued an Authorization to Operate letter. (System should not be turned on until ATO is received.)